An official website of the United States government
Here's how you know
A .mil website belongs to an official U.S. Department of Defense organization in the United States.
A lock (lock ) or https:// means you’ve safely connected to the .mil website. Share sensitive information only on official, secure websites.

NMCB 133 Restores Coastline

20 October 2020

From MC1 Jamica Johnson

Naval Mobile Construction Battalion (NMCB) 133 has taken the baton in the race to complete Naval Station (NAVSTA) Rota's Cliff Erosion Repair project. The multi-year project aims at strengthening the integrity of nearly a kilometer of the NAVSTA Rota's coastline.

Naval Mobile Construction Battalion (NMCB) 133 has taken the baton in the race to complete Naval Station (NAVSTA) Rota's Cliff Erosion Repair project.  The multi-year project aims at strengthening the integrity of nearly a kilometer of the NAVSTA Rota's coastline. The project started in January of 2018, with NMCB 133 being the first battalion to take on the task, and three years later, they are back in Rota and charging forward.

The Bees' ultimate goal is to build a stone berm, a raised stretch of land that protects the cliff's base, to stabilize naturally. The highest point of the structure is an estimated 5.8 meters, to handle high tide, withstanding waves of 8 to 12 feet.

"We have a mixed crew, so we have about three guys who were out here working on our last deployment, and the rest of our crew is new to this project," said Equipment Operator 1st Class Richard Brown. “It’s good because it brings experience as well as new insights to the project.”

Base officials began noticing the cliff erosion in the 1960s, and in the last decade, the rate of deterioration and impacts to base facilities have rapidly increased, NMCB 133's Command Master Chief, Helen Daniel, spoke about being deployed to Rota with NMCB 133 as an Equipment Operator Constructionman in 1995.

“We wanted to try and slow the erosion using tetrapods, which are large concrete similar to the design of toy jacks, that are often used along shorelines to decrease erosion," said Daniel.

 “We couldn’t move the tetrapods with the crane due to the location.”

Brown explains how the stone berm is built, "We take one sheet of Geotech fabric and lay it across the sand. Then we take pebble gravel and lay that on top. We follow up with another Geotech layer, then our quarry rock, to complete it.”

From 2018 until now, the cliff's edge had moved within 110 yards of a fuel tank used to supply U.S., Spanish, and other partnering nations' ships throughout the Mediterranean.  In addition to compromising the fuel tank, the erosion has contributed to the loss of base housing. As the cliff further erodes inland, it has caused more destruction of base housing, roadways, playgrounds, and sewer lines.

"You can see the debris from when the houses went [over the cliff]. You can see the road that's fallen," said Brown.

The shoreline's erosion has started to spread to property off base, causing damage to Rota's local province.

“While it is slightly out of the norm for us, as the cliff extends past the property line of the base, this project is a great opportunity for our troops to build on their skills in a real-world situation while giving back to the local community," said Daniel.  "It's also great to see the level of trust and partnership we have built with our host nation that they would let us lead a mission of this much importance." 

Rota, Spain's coastline is a natural habitat for many forms of wildlife to include an endangered chameleon species, during repair the construction crew must maintain, and protect, the open and livable environment for the wildlife.

The region is also rich in history. The cliff looks over the Bay of Cadiz, named after Cadiz, just across the water. Cadiz is one of the oldest cities in Western Europe. Due to its longevity, there are many ruins and potential for discoveries of times long past. A local archaeological monitor has been on-site to ensure personnel take care of any potential remains or ruins that might become uncovered.

"You can see some of the ruins coming out of the water, one of the new things we have found are whale bones," Brown explained.

The cliff’s erosion has caused a total of more than $10 million dollars in damage, with a distance of 93.3 meters lost due to erosion. The project is scheduled to be complete by of August 2021.

NMCB 133 is a subordinate command of the Navy Expeditionary Combat Force (NECF), executing construction and engineering projects in support of airfield damage repair, building and maintaining critical infrastructure; and providing power, water, and other essential commodities in the U.S. 6th Fleet, Area of Operation. The NECF is strengthened by the support of the American public and values opportunities to increase public awareness and understanding of the Navy through participation in community outreach events nationwide.

 

Google Translation Disclaimer

  • Google Translate, a third party service provided by Google, performs all translations directly and dynamically.
  • Commander, Navy Region Europe, Africa, Central, cnreurafcent.cnic.navy.mil has no control over the features, functions, or performance of the Google Translate service.
  • The automated translations should not be considered exact and should be used only as an approximation of the original English language content.
  • This service is meant solely for the assistance of limited English-speaking users of the website.
  • Commander, Navy Region Europe, Africa, Central, cnreurafcent.cnic.navy.mil does not warrant the accuracy, reliability, or timeliness of any information translated.
  • Some items cannot be translated, including but not limited to image buttons, drop down menus, graphics, photos, or portable document formats (pdfs).
  • Commander, Navy Region Europe, Africa, Central, cnreurafcent.cnic.navy.mil does not directly endorse Google Translate or imply that it is the only language translation solution available to users.
  • All site visitors may choose to use similar tools for their translation needs. Any individuals or parties that use Commander, Navy Region Europe, Africa, Central, cnreurafcent.cnic.navy.mil content in translated form, whether by Google Translate or by any other translation services, do so at their own risk.
  • IE users: Please note that Google Translate may not render correctly when using Internet Explorer. Users are advised to use MS Edge, Safari, Chrome, or Firefox browser to take full advantage of the Google Translate feature.
  • The official text of content on this site is the English version found on this website. If any questions arise related to the accuracy of the information contained in translated text, refer to the English version on this website, it is the official version.

Commander, Navy Region Europe, Africa, Central   |   PSC 817, Box 108   |   FPO, AE 09622
Official U.S. Navy Website